General
More Pipelines Arrive Kaduna Ahead Of The $2.8bn AKK Gas Project Ground Breaking
The Ajaokuta-Kaduna-Kano (AKK) pipeline is a 614km-long natural gas pipeline currently being developed by the Nigerian National Petroleum Corporation (NNPC).
It is set to be laid between Ajaokuta and Kano in Nigeria and forms phase one of the Trans-Nigeria Gas Pipeline (TNGP) project.
The pipeline project is being implemented via a build and transfer (BT) public-private partnership (PPP) model, which involves the contractor providing 100% of the funding.
The pipeline will cost an estimated $2.8bn and ground breaking ceremony is scheduled for tuesday 30th June.
The project will result in the establishment of a connecting pipeline network between the eastern, western and northern regions of Nigeria.
It also aims to create a steady and guaranteed gas supply network between the northern and southern parts of Nigeria by utilising the country’s widely available gas resources.
NNPC originally announced tenders for the development of the AKK pipeline in July 2013.
A project proposal was submitted to the Infrastructure Concession Regulatory Commission (ICRC) in June 2017.
The PPP compliance certificate was issued in July 2017 along with the approval of the feasibility study.
The Federal Executive Council (FEC) granted approval for the project in December 2017.
-
Technology2 years ago
VoIP Number: Everything You Need To Know
-
Music2 months ago
[Music] Gnash Ft Olivia O’Brien – I Hate you, I Love you
-
Music2 months ago
[INSTRUMENTAL] John Legend – All Of Me
-
Music2 months ago
Alan Walker – Faded [INSTRUMENTAL]
-
Music2 months ago
[Video] 21 Savage ft. Offset & Metro Boomin – Rap Saved Me
-
Music2 months ago
[Instrumental] Wiz Khalifa – See You Again ft. Charlie Puth
-
ANE Stories4 months ago
[STORY] AMAKA THE LESBIAN (Complete Episodes)
-
Music2 months ago
[Music] Akon – Sorry Blame It On Me